Legislation Details

File #: 26-0192    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 12/22/2025 In control: Commissioners Court
On agenda: 1/8/2026 Final action: 1/8/2026
Title: Request for approval of a change in contract with J Rivas Construction LLC., in connection with Denver Harbor Park - Park Improvements - 2023, with no change in the contract amount, Job No. 22/0064-1, UPIN 24102MF35101, Precinct 2, MWBE Contracted Goal: 15%, MWBE Current Participation: 95.04%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 22/0064, UPIN 24102MF35101
Vendor/Entity Legal Name (if applicable): J Rivas Construction, LLC

MWBE Contracted Goal (if applicable): 15%
MWBE Current Participation (if applicable): 95.04%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
...title
Request for approval of a change in contract with J Rivas Construction LLC., in connection with Denver Harbor Park - Park Improvements - 2023, with no change in the contract amount, Job No. 22/0064-1, UPIN 24102MF35101, Precinct 2, MWBE Contracted Goal: 15%, MWBE Current Participation: 95.04%.
...end

Background and Discussion:
This On-Call Term Contract for Concrete Sidewalk and Related Items in Harris County includes, but is not limited to, the construction of concrete sidewalks, concrete pavement, traffic striping and pavement markings, and associated improvements. For the Denver Harbor Park Improvement Project, the contractor shall remove the existing asphalt trail and replace it with a new concrete trail, install park benches, upgrade the parking lot, install new park signage, and provide striping and pedestrian-crossing improvements at the trail connection point to the adjacent street.

PCO#1 - The new bid items were not included in the original On-Call Contract and would typically require formal addition through the FCR and PO amendment process since this is a money contract. However, the contract has already been amended through the referenced process. Therefore, the addition of thes...

Click here for full text