Legislation Details

File #: 26-0186    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 12/22/2025 In control: Commissioners Court
On agenda: 1/8/2026 Final action: 1/8/2026
Title: Request for approval of a change in contract with Precise Services, Inc., in connection with HCSFNC - TO6 - Connorvale Development, with an addition in the amount of $64,500.00, Job No. 24/0139-4, UPIN 21289MF1Z501, Precinct 2, MWBE Contracted Goal: 25.22%, MWBE Current Participation: 100%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0139, UPIN 21289MF1Z501

Vendor/Entity Legal Name (if applicable): Precise Services, Inc.
MWBE Contracted Goal (if applicable): 25.22%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Precise Services, Inc., in connection with HCSFNC - TO6 - Connorvale Development, with an addition in the amount of $64,500.00, Job No. 24/0139-4, UPIN 21289MF1Z501, Precinct 2, MWBE Contracted Goal: 25.22%, MWBE Current Participation: 100%.
end

Background and Discussion:
In response to the destruction wrought by Hurricane Harvey that underscored critical shortages in Harris County's inventory of affordable homes, Harris County's Single-Family New Construction Program (SFNCP) matches individuals and families with opportunities to purchase new affordable homes in growing developments throughout the county. Task Order 6: includes construction of roadways and sidewalks, Installation of sanitary sewer and storm systems, Pavement improvements, Construction of a lift station and detention ponds.

This change order is tied to PCO -10 and 11. PCO-10 includes installing sod around concrete structures and along the detention pond perimeters to prevent erosion, at a cost of $25,000, and extending the Floatable Collection Screen by 4 feet to resolve field discrepancies, adding $5,000, for a total of $30,000.
PCO-11 addresses a resident's safety concern b...