Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Transmittal
Project ID (if applicable): Z100-00-00-X300
Vendor/Entity Legal Name (if applicable): N/A
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Transmittal by the Flood Control District of a certificate of substantial completion with Lecon, Inc., for general repairs in North Harris County (Project ID Z100-00-00-X300, Job No. 24/0122, Precincts 3 and 4).
end
Background and Discussion:
The purpose of this transmittal is to submit the Certificate of Substantial Completion when the Contractor has completed the scope of work of a job and has addressed and completed all punch list items to the satisfaction of the Flood Control District.
Expected Impact:
The completed work will allow the contractor to construct the project so that Harris County can realize intended flood risk reduction benefits in North Harris County.
Alternative Options:
There is no viable alternative to accepting substantial completion when a contractor successfully completes the work scope of a contract.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Economy Initiative (Goal 3): N/A
Health Initiati...