Legislation Details

File #: 26-0118    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 12/19/2025 In control: Commissioners Court
On agenda: 1/8/2026 Final action: 1/8/2026
Title: Request for approval of an amendment to an agreement with CenterPoint Energy Resources Corp. dba CenterPoint Energy Texas Gas Operations in the amount of $12,145.45, for utility adjustments at Lawndale Street, near HCFCD Unit D100-00-00 (Brays Bayou Watershed, Bond ID C-11, Project ID D100-00-00-B047, Agreement No. 2020-24, Precinct 2).
Attachments: 1. 010826 AMEND CENTERPOINT 2020-24 PCT 2 backup.pdf

Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): D100-00-00-B047
Vendor/Entity Legal Name (if applicable): CenterPoint Energy Resources Corp. dba CenterPoint Energy Texas Gas Operations

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of an amendment to an agreement with CenterPoint Energy Resources Corp. dba CenterPoint Energy Texas Gas Operations in the amount of $12,145.45, for utility adjustments at Lawndale Street, near HCFCD Unit D100-00-00 (Brays Bayou Watershed, Bond ID C-11, Project ID D100-00-00-B047, Agreement No. 2020-24, Precinct 2).
end

Background and Discussion:
CenterPoint Energy Resources Corp. dba CenterPoint Energy Texas Gas Operations (CenterPoint Gas) is requesting the Flood Control District to seek authorization from the Harris County Commissioners Court to pay the additional amount of $12,145.45 that exceeded the estimated cost of $6,620.26 as shown in the original agreement. The additional amount was due to overruns in material and labor costs that were not expected during the development of the estimate.

Expected Impact:
This amendment will allow the Flood Control District to pay CenterPoint Gas for the additional amount required to cover relocation expenses.

Alternative Options:
The alternative to approving this item would be for the Flood Control District to not pay CenterPoint Gas

County Strategic Plan Goal: 2. Connect our community with safe, r...

Click here for full text