Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 23/0323, UPIN 211033952830022
Vendor/Entity Legal Name (if applicable): James Construction Group, LLC
MWBE Contracted Goal (if applicable): 12%
MWBE Current Participation (if applicable): 13.08%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with James Construction Group, LLC in connection with Bridge Construction - Greenhouse Road over Cypress Creek - K100-00-00 - 2021, with an addition in the amount of $18,014.61, Job No. 23/0323-2, UPIN 211033952830022, Precinct 3, MWBE Contracted Goal: 12%, MWBE Current Participation: 13.08%.
end
Background and Discussion:
The project consists of the design and construction of the northbound bridge and approaches along Greenhouse Road over Cypress Creek. The project limits are from 0.3 miles north of Winding Willow Oak Way to 0.3 miles south of Mound Rd which primarily consists of a bridge that is 1,800 feet in length. This proposed bridge typical section will be a mirror image of the existing southbound bridge which is approximately 1,800 feet with 17 spans and includes a 20-foot approach slab at each end.
To prevent water from draining off the bridge onto the sidewalk, the drainage system was extended under the sidewalk and connected to a Type A inlet. In addition, a retaining wall was added to protect the adjacent bank under the new bridge and along the proposed sidewalk from erosion. This change in contract will allow contractor ...
Click here for full text