Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., CFM, ENV-SP, County Engineer
Secondary Department: Commissioner, Precinct 4
Secondary Department Head/Elected Official: Lesley Briones
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): UPIN 24104MF37701
Vendor/Entity Legal Name (if applicable): DECON LLC
MWBE Contracted Goal (if applicable): 16.94%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute a professional services agreement with DECON LLC, in the amount of $1,737,954.00 for Detailed Design Services in connection with the Bus Shelter Improvements - Universal Accessibility Bus Stop Improvement - 2023, UPIN 24104MF37701, Precinct 4, MWBE Contracted Goal: 16.94%.
end
Background and Discussion:
DECON LLC will be responsible for delivering the detailed design of the selected shelter concepts from Phase 1. DECON LLC will coordinate with and follow the Office of the County Engineering (OCE) and METRO's established standards and guidelines for the 250 shelter-ready locations across HCP4.
The Consultant will provide architectural, structural, and civil detail designs for new bus shelters, shelter
furnishings, and amenities that comply with METRO design standards at up to 250 shelter-ready locations
to be used across Precinct 4. The process and scope of services are:
Task 1: Project Management and Coordination
Task 2: Fieldwork for 250 shelter locations
Task 3: 50% Detail Design Development
Task 4: 100% Detail Design Structural & Architectural
Task 5: 100% Civil Detail Design Development
Task 6: Bid Phase
Expected Impact:
The project goal is to pr...