Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 24/0373, UPIN- 23102MF2UN01
Vendor/Entity Legal Name (if applicable): Environmental Allies, Inc.
MWBE Contracted Goal (if applicable): 32.17%
MWBE Current Participation (if applicable): 20.96%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Environmental Allies, Inc., in connection with Roadway - Blackhawk Blvd - Scarsdale Blvd to Sam Houston Pkwy - P2 - 2022, adding 15 calendar days, with an addition in the amount of $12,699.53, Job No. 24/0373-1, UPIN 23102MF2UN01, Precinct 2, MWBE Contracted Goal: 32.17%, MWBE Current Participation: 20.96%.
end
Background and Discussion:
Harris County intends to provide improvements to Blackhawk Boulevard from Scarsdale Boulevard to South Sam Houston Parkway East, within Precinct 2 including sidewalks, replacing damaged roadway pavement, new curb ramps, etc.
This change order is tied to PCO 1 and 2. PCO 1 is for the replacement of manhole covers to be the City of Houston with their logo. Per the Engineer of Record, we are increasing the size of the manholes from the planned 24" rings to 32" rings. This change is a result of elevation discrepancies that prevented the use of 24" rings and lids within the sidewalks. The additional cost for this change totals $32,299.53, representing 1.22 % of the total project budget and an additional time extension of 15 days. PCO 2 is for the removal of the bid item 28 from the contract for the adju...