Legislation Details

File #: 25-7590    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 11/21/2025 In control: Commissioners Court
On agenda: 12/11/2025 Final action: 12/11/2025
Title: Request for approval to execute an agreement with HR Green, Inc. in the amount of $467,924.00, for professional engineering services in connection with Drainage Study - Hunterwood Village 1 - 2024 - UPIN 25102MF3QU01, Precinct 2, MWBE Contracted Goal: 6.68%.
Sponsors: Mony Hossain
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official:

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): UPIN 25102MF3QU01
Vendor/Entity Legal Name (if applicable): HR Green, Inc.

MWBE Contracted Goal (if applicable): 6.68%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with HR Green, Inc. in the amount of $467,924.00, for professional engineering services in connection with Drainage Study - Hunterwood Village 1 - 2024 - UPIN 25102MF3QU01, Precinct 2, MWBE Contracted Goal: 6.68%.
end

Background and Discussion:
Harris County Precinct 2 (PCT2) has requested that the Harris County Engineering Department (HCED) to prepare study documents for Drainage Study - Hunterwood Village 1 - 2024 project in Harris County, Texas, Precinct 2. Hunterwood Village 1 Subdivision is bounded by Lake Houston Parkway to the west, US 90 to the south and Sulphur Gully HCFCD Unit P109-00-00 to the east. Hunterwood Village 1 is an older subdivision built in the late 1970's served by curb and gutter roads with storm sewers. The subdivision is located within the City of Houston city limits; therefore, the study will follow City of Houston criteria and methodology. The scope of this project is to evaluate the existing drainage system and identify the sources of flooding issues within the subdivision. The analysis will include the area surrounding the subdivision including the outfall channel, Sulphur Gully. The purpose of the drainage study is to develop a recommendation that efficien...

Click here for full text