Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom Ramsey, P.E.
Regular or Supplemental RCA: Regular RCA
Type of Request: Financial Authorization
Project ID (if applicable): 15104M23NP03
Vendor/Entity Legal Name (if applicable): BNSF RAILWAY COMPANY
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of an amendment and renewal of the agreement with BNSF Railway Company to account for the inflationary cost increase of $404,601 from the original agreement, in connection with the proposed widening of the existing Hufsmith-Kohrville Road at-grade crossing, UPIN 15104M23NP03, Precinct 3.
end
Background and Discussion:
The Hufsmith-Kohrville Road Segment 3A project includes roadway widening and associated railroad crossing improvements. The original agreement with BNSF Railway Company covered design review, inspection, and construction costs based on 2021 rates.
In 2021, at the time of the initial agreement (approved on April 27, 2021), the total project cost approved by BNSF was $935,496. Due to revised rates and inflation adjustments, the current total cost in 2025 has increased to $1,340,097, resulting in an amendment amount difference of $404,601. Since that time, BNSF has updated its cost schedule to reflect current labor, materials, and administrative expenses. This amendment aligns the County's agreement with the revised 2025 cost structure, ensuring continued coordination and compliance with BNSF's construction and safety requirements for the at-grade crossin...