Legislation Details

File #: 25-7536    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/20/2025 In control: Commissioners Court
On agenda: 12/11/2025 Final action: 12/11/2025
Title: Request for approval of a change in contract with Platinum Paving, LLC, in connection with Pedestrian Improvements - Various Locations - 2023, adding 69 calendar days, with an addition in the amount of $74,093.99, Job No. 24/0260-2, UPIN 24208MF33Z01, Precinct 3, MWBE Contracted Goal: 64%, MWBE Current Participation: 30.12%.
Attachments: 1. CIC-24208MF33Z01-Pedestrian Improv-24-0260-2-Platinum Pav-P3-12112025.pdf
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0260, UPIN 24208MF33Z01
Vendor/Entity Legal Name (if applicable): Platinum Paving, LLC

MWBE Contracted Goal (if applicable): 64%
MWBE Current Participation (if applicable): 30.12%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Platinum Paving, LLC, in connection with Pedestrian Improvements - Various Locations - 2023, adding 69 calendar days, with an addition in the amount of $74,093.99, Job No. 24/0260-2, UPIN 24208MF33Z01, Precinct 3, MWBE Contracted Goal: 64%, MWBE Current Participation: 30.12%.
end

Background and Discussion:
The Pedestrian Improvements - Various Locations project consists of replacing the existing rail with up-to-date railing standard, sidewalk replacement and placing new sidewalk in various locations within Harris County. Major work activities include removal of existing guardrail, removal of handrail, concrete sidewalk, concrete curb ramp, Metal Beam Guardrail Fence with Mow Strip, Pedestrian and Traffic railing replacement to the up-to-date standard in Harris County - Precinct 3.

The Changes in contract include:
* A new line item is needed to Sawcut existing concrete sidewalk and Install PR11 Foundation to complete the work proposed per the revised plan with an additional cost of $13,161.60 and 21 Calendar days.
* A new line item is needed to provide a 12-inch foundation for the combination Rail and sidewalk to complete the work proposed per ...

Click here for full text