Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD
Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom Ramsey
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 250302
Vendor/Entity Legal Name (if applicable): Durwood Greene Construction Co.
MWBE Contracted Goal (if applicable): 31.56%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.
Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of lowest bid meeting specifications to Durwood Greene Construction Co. in the amount of $2,554,089 for asphalt rehabilitation for Memorial Drive between San Felipe and West of Chimney Rock (2024) for Precinct 3, and for the County Clerk to execute any applicable bonds to be received (250302), MWBE Contracted Goal: 31.56%.
end
Background and Discussion: Request for approval of an award on the basis of low bid to Durwood Greene Construction Co. for Asphalt Rehabilitation for Memorial Drive between San Felipe and West of Chimney Rock (2024) for Harris County Precinct 3, and for the County Clerk to execute any applicable bonds to be received (250302), MWDBE Contracted Goal: 31.56%.
The low bidder, Ceballos Construction, LLC, did not meet the qualifications included in the bid package. In order to bid on this project, contractors/bidders must be prequalified on the day of the Bid Opening through TXDOT. Based on the bid results, the recommendation of OCE and the design consultant, WSB, LLC, it is recommended that the lowest responsive bidder, Durwood Greene Construction Co., be awarded the contract.
Expected Impact: Awarding the contract will allow the recommended bidder to proceed with constru...
Click here for full text