Legislation Details

File #: 25-7530    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/20/2025 In control: Commissioners Court
On agenda: 12/11/2025 Final action: 12/11/2025
Title: Request for approval of a change in contract with Texas Materials Group, Inc., in connection with final construction of Transportation Improvements near University of Houston - Cullen Blvd (Seg B) from S. of Wheeler Ave to IH45 - 2019, adding 6 calendar days, with a deduction in the amount of $580,975.50, Job No. 20/0124-4, UPIN 19101MF19201, Precinct 1.
Attachments: 1. CIC-19101MF19201-UofH Cullen-20-0124-4.final-Texas Materials-P1-12112025.pdf
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 20/0124, UPIN 19101MF19201
Vendor/Entity Legal Name (if applicable): Texas Materials Group, Inc.

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Texas Materials Group, Inc., in connection with final construction of Transportation Improvements near University of Houston - Cullen Blvd (Seg B) from S. of Wheeler Ave to IH45 - 2019, adding 6 calendar days, with a deduction in the amount of $580,975.50, Job No. 20/0124-4, UPIN 19101MF19201, Precinct 1.
end

Background and Discussion:
This project is a transportation improvement project for Transportation Improvements near University of Houston - Cullen Blvd (Seg B) from S. of Wheeler Ave to IH45, which includes the reconstruct of Cullen Boulevard, new underground storm sewer systems, new 12 foot shared-use patch, 1 new signal, signal modification at 6 intersections, installation of landscaping irrigation system and new street lights in Precinct 1.

This change in contract includes the final accounting of bid items for a final payment.

The substantial completion date for the project will be set for Sept 16, 2024. In accordance with Section 5.3 of the General Conditions, (1) time of the essence, and (2) delay damages will apply past the new substantial completion date.


Expected Impact:
Changes will allow for...