Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 20/0124, UPIN 19101MF19201
Vendor/Entity Legal Name (if applicable): Texas Materials Group, Inc.
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Texas Materials Group, Inc., in connection with final construction of Transportation Improvements near University of Houston - Cullen Blvd (Seg B) from S. of Wheeler Ave to IH45 - 2019, adding 6 calendar days, with a deduction in the amount of $580,975.50, Job No. 20/0124-4, UPIN 19101MF19201, Precinct 1.
end
Background and Discussion:
This project is a transportation improvement project for Transportation Improvements near University of Houston - Cullen Blvd (Seg B) from S. of Wheeler Ave to IH45, which includes the reconstruct of Cullen Boulevard, new underground storm sewer systems, new 12 foot shared-use patch, 1 new signal, signal modification at 6 intersections, installation of landscaping irrigation system and new street lights in Precinct 1.
This change in contract includes the final accounting of bid items for a final payment.
The substantial completion date for the project will be set for Sept 16, 2024. In accordance with Section 5.3 of the General Conditions, (1) time of the essence, and (2) delay damages will apply past the new substantial completion date.
Expected Impact:
Changes will allow for...