Legislation Details

File #: 25-7529    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/20/2025 In control: Commissioners Court
On agenda: 12/11/2025 Final action: 12/11/2025
Title: Request for approval of a change in contract with Texas Wall & Landscape, LLC, in connection with final construction of Townsen Park-n-Ride Multimodal Connector, adding 3 calendar days, with an addition in the amount of $150,866.85, Job No. 23/0268-3, UPIN 14104MF0AV01, Precinct 3.
Attachments: 1. CIC-14104MF0AV01-Townsen ParknRide-23-0268-3.final-Texas Wall-P3-12112025.pdf
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0268, UPIN 14104MF0AV01
Vendor/Entity Legal Name (if applicable): Texas Wall & Landscape, LLC

MWBE Contracted Goal (if applicable): 0%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Texas Wall & Landscape, LLC, in connection with final construction of Townsen Park-n-Ride Multimodal Connector, adding 3 calendar days, with an addition in the amount of $150,866.85, Job No. 23/0268-3, UPIN 14104MF0AV01, Precinct 3.
end

Background and Discussion:
The project consists of construction of multimodal connector trail that will connect Spring Creek Greenway Hike and Bike trail to Townsen Park and Ride as well as to the historical US 59 bridge crossing the San Jacinto River in Harris County Precinct 3.

The change in contract includes the following:
* Sheet pile (safety trench system) - $27,688.96 and 3 additional days.
* ADA STYLE GRATES - 2EA x $765.08/EA = $1,530.16
* Adding new pay item for dewatering - $6,753,.50
* Adding new pay item for installation of sodding block - 600SY x $719/SY = $4,314.00
* Adding new pay item for HYDROMULCH SEEDING - 6,525SY x $1.83/SY = $11,940.75
* Adding new pay item for WATERING - 80MGL x $122/MGL = $9,760.00
* Adding new pay item for TRAFFIC CONTROL - 1LS x $12,992.45 = $12,992.45
* The final adjustment (reconciliation of actual quantities used in construction against the bid quantities). ($75,88...