Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Adrian Garcia, Commissioner
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 25103MF3XC01
Vendor/Entity Legal Name (if applicable): AGHA Engineering LLC
MWBE Contracted Goal (if applicable): 17.78%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with AGHA Engineering LLC in the amount of $217,861.10 for Professional Engineering Services in connection with Park Improvement - Baytown Soccer Complex - 2025, UPIN 25103MF3XC01, Precinct 3, MWBE Contracted Goal: 17.78%.
end
Background and Discussion:
The County seeks AGHA Engineering LLC to develop a park master plan as well as design a parking lot, a connecting road, and additional ball fields.
Expected Impact:
Executing the agreement will allow AGHA Engineering LLC to develop a park master plan as well as design a parking lot, a connecting road, and additional ball fields.
Alternative Options:
An alternative would be to not develop a park master plan or design a parking lot, a connecting road, and additional ball fields. This will result in an undesirable condition.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): F1: Strengthen the County's commitment to Vision Zero principles and goals.
Economy Ini...
Click here for full text