Title: Request for approval of a certain project, decreeing the project to be a public necessity and convenience, directing the Harris County Real Property Division to acquire, two (2) traffic signal easement tracts for the public project known as Traffic Signal - Fairbanks North Houston Rd. at West Rd. - 2022, for the purpose of rebuilding a traffic signal at the intersection of Fairbanks N Houston at West Rd, UPIN 23101MF2S401, Precinct 1.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: Not applicable

Regular or Supplemental RCA: Regular RCA

Type of Request: Public Necessity

Project ID (if applicable): 23101MF2S401
Vendor/Entity Legal Name (if applicable): Any applicable landowner and/or property interest holder

MWBE Contracted Goal (if applicable): Not applicable
MWBE Current Participation (if applicable): Not applicable
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): Not applicable
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a certain project, decreeing the project to be a public necessity and convenience, directing the Harris County Real Property Division to acquire, two (2) traffic signal easement tracts for the public project known as Traffic Signal - Fairbanks North Houston Rd. at West Rd. - 2022, for the purpose of rebuilding a traffic signal at the intersection of Fairbanks N Houston at West Rd, UPIN 23101MF2S401, Precinct 1.
end

Background and Discussion:
Traffic signals are re-built to improve the operation of an intersection and better facilitate pedestrian activities. The existing signal uses outdated and degrading equipment and does not adequately accommodate pedestrian crossings. Re-building this signal will ensure the intersection is brought up to compliance with current standards and will provide pedestrian connectivity.

Expected Impact:
Re-building the traffic signal will bring the infrastructure to current standards and specifications and reduce overall maintenance cost. It will also significantly reduce the risk of failure during a catastrophic event.

Alternative Options:
To continue to maintain the existing traffic signal a...