Legislation Details

File #: 25-7121    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 10/29/2025 In control: Commissioners Court
On agenda: 11/13/2025 Final action: 11/13/2025
Title: Request for approval of a change in contract with MC2 Civil, LLC, in connection with Treaschwig Rd A (Phase 1) - from 1,000' west of Aldine Westfield Rd to west of Cypress Creek - 2014, adding 14 calendar days, with an addition in the amount of $563,003.63, Job No. 23/0420-2, UPIN 14104MF08X01, Precinct 3, MWBE Contracted Goal: 27%, MWBE Current Participation: 29.88%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0420, UPIN 14104MF08X01
Vendor/Entity Legal Name (if applicable): MC2 Civil, LLC

MWBE Contracted Goal (if applicable): 27%
MWBE Current Participation (if applicable): 29.88%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with MC2 Civil, LLC, in connection with Treaschwig Rd A (Phase 1) - from 1,000' west of Aldine Westfield Rd to west of Cypress Creek - 2014, adding 14 calendar days, with an addition in the amount of $563,003.63, Job No. 23/0420-2, UPIN 14104MF08X01, Precinct 3, MWBE Contracted Goal: 27%, MWBE Current Participation: 29.88%.
end

Background and Discussion:
The project consists of construction of Treaschwig Road Segment A Phase 1 project consists of reconstruction and widening of Treaschwig Rd. from a 2-lane asphalt to a 4-lane concrete roadway from 1000' west of Aldine Westfield to west of Cypress Creek. Additionally, extend intersection improvements at Aldine Westfield by 500' North and South of Treaschwig Road. Project will construct a wet bottom detention pond adjacent to Cypress Creek.

This change in contracts includes:
PCO #4 (RFI #27) - Extension of Line Item 50 for two additional collars required to overcome a utility conflict and redirect manhole angles. Cost: $4,000.00
PCO #5 (RFI #25) - Additional work required to tie in existing RCP pipe to new proposed manhole. Cost: $6,811.08
PCO #6 (RFI #17) - Conflict between a 42" RCP and a 12" waterline ...

Click here for full text