Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 24/0077, UPIN 24208MF30X01
Vendor/Entity Legal Name (if applicable): Environmental Allies, Inc.
MWBE Contracted Goal (if applicable): 19.56%
MWBE Current Participation (if applicable): 4.03%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Environmental Allies, Inc., in connection with final construction of Intersection Improvement - West Cypress Forest Drive at Cypresswood Drive - 2023, with an addition in the amount of $67,722.12, Job No. 24/0077-1, UPIN 24208MF30X01, Precinct 3, MWBE Contracted Goal: 19.56%, MWBE Current Participation: 4.03%.
end
Background and Discussion:
The project involved extending existing box culverts using concrete collars to a length that permitted the removal of the guardrail and allowed the ditches to be graded to the new terminus points with safe, easily maintainable slopes. The Office of the County Engineer's Construction Programs Division team oversaw the work. Changes include reconciliation of actual quantities used in construction with the estimated quantities included for bidding purposes.
PCO-14: install Retaining wall w/ slope
Cost: $28,525.39/EA Quantity = 1, 0-days
PCO-15: cast-in-place transition piece to connect the precast SETs to the culvert boxes,
Cost: $26,397.59/EA Quantity = 1, 0-days
PCO-13: Final Adjustment: $12,799.14
Expected Impact:
Changes allow for addition of new bid items to complete th...