Legislation Details

File #: 25-6872    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 10/17/2025 In control: Commissioners Court
On agenda: 10/30/2025 Final action: 10/30/2025
Title: Request for approval of a change in contract with ECM Construction, LLC, in connection with the final construction of Sidewalk - N. Eldridge Pkwy - 2022, adding 54 calendar days, with a deduction in the amount of $33,186.25, Job No. 24/0224-2, UPIN 23103MF2RP01, Precinct 3, MWBE Contracted Goal: 13.05%, MWBE Current Participation: 100%.
Sponsors: Mony Hossain
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0224, UPIN 23103MF2RP01
Vendor/Entity Legal Name (if applicable): ECM Construction, LLC

MWBE Contracted Goal (if applicable): 13.05%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with ECM Construction, LLC, in connection with the final construction of Sidewalk - N. Eldridge Pkwy - 2022, adding 54 calendar days, with a deduction in the amount of $33,186.25, Job No. 24/0224-2, UPIN 23103MF2RP01, Precinct 3, MWBE Contracted Goal: 13.05%, MWBE Current Participation: 100%.
end

Background and Discussion:
This project involves the construction of sidewalks along North Eldridge Parkway from Spencer Road (FM 529) to West Road, and along West Road from North Eldridge Parkway to 940 feet East (Precinct 3). This project is federally funded by the U.S. Housing and Urban Development Department (HUD) through the Harris County Community Services Department (HCCSD).

This final change order is for a deduction of the final adjustment in the amount of $33,186.25 and includes quantity adjustments of existing items for final values. Final Adjustment is the reconciliation of actual quantities used in construction against the bid quantities.

The final change in contract includes the following:
PCO #5 Interceptor addition request-Riser $4,150.00 Time: 5 Days
PCO #6 AT&T Utility Conflict Delay $0 Time: 49 Days
PCO #7 Final Adjustment ...