File #: 25-6871    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 10/17/2025 In control: Commissioners Court
On agenda: 10/30/2025 Final action: 10/30/2025
Title: Request for approval of a change in contract with Traffic Systems Construction, Inc., in connection with final construction of Intersection Improvement - South Fry Boulevard at Westheimer Parkway - 2022, adding 219 calendar days, with a deduction in the amount of $26,429.34, Job No. 23/0177-1, UPIN 22104MF2JY01, Precinct 4, MWBE Contracted Goal: 30%, MWBE Current Participation: 68.77%.
Sponsors: Mony Hossain
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0177, UPIN 22104MF2JY01
Vendor/Entity Legal Name (if applicable): Traffic Systems Construction, Inc.

MWBE Contracted Goal (if applicable): 30%
MWBE Current Participation (if applicable): 68.77%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Traffic Systems Construction, Inc., in connection with final construction of Intersection Improvement - South Fry Boulevard at Westheimer Parkway - 2022, adding 219 calendar days, with a deduction in the amount of $26,429.34, Job No. 23/0177-1, UPIN 22104MF2JY01, Precinct 4, MWBE Contracted Goal: 30%, MWBE Current Participation: 68.77%.
end

Background and Discussion:
Project includes construction of intersection improvements including additional left turn lanes, dedicated right turn lanes, pedestrian crossing improvements with ADA ramps, additional sidewalks, traffic signal modifications, etc.

The final change order will add 219 days that were delays caused by outside factors including limited working times dictated by Precinct along with delayed inspections from Traffic for signal modifications. This intersection is one of six intersections that were awarded as a package and all 6 intersections had separate Purchase Orders. This causes all 6 to run concurrently per the award of the contract. All 6 intersections experienced the same delays thus resulting in the addition of time to the contract as a whole on all 6 final Pay Est...