Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Report
Project ID (if applicable): 20104MF1BM01
Vendor/Entity Legal Name (if applicable): Arcadis, U.S., Inc.
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.
Request Summary (Agenda Caption):
title
Request for approval of a Study Report prepared by Arcadis, U.S., Inc. for Grant Road Segment 4 - from Cypress Rose Hill Road to Telge Road - 2018, UPIN 20104MF1BM01, Precinct 3.
end
Background and Discussion:
This project is located at Grant Road in Precinct 3 and is adjacent to other capital improvement projects.
Expected Impact:
This Study Report will provide the necessary information to proceed with the proposed road improvement project which consists of a 4-lane concrete boulevard in a 100-foot ROW with a 32-foot raised median, underground storm sewer, detention mitigation, and sidewalks.
Alternative Options:
The County could elect to approve or choose to reject the study recommendations. However, if not approved, the design plans cannot be completed as recommended in the study.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: F: Ensure safety and security for all using the county's transportation network in alignment with the County's Vision Zero plan.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): F1: Strengthen the County's commitment to Vision Zero principles and goals...
Click here for full text