Legislation Details

File #: 25-6800    Version: 1 Name:
Type: Report Status: Passed
File created: 10/15/2025 In control: Commissioners Court
On agenda: 10/30/2025 Final action: 10/30/2025
Title: Request for approval of a Study Report prepared by AKV Consultants LLC for Market Street from Lakeside Drive to Magnolia Street, UPIN 23102MF2UQ01, Precinct 2.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

Secondary Department: Choose an item.
Secondary Department Head/Elected Official:

Regular or Supplemental RCA: Regular RCA

Type of Request: Report

Project ID (if applicable): 23102MF2UQ01
Vendor/Entity Legal Name (if applicable): AKV Consultants LLC

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.

Request Summary (Agenda Caption):
title
Request for approval of a Study Report prepared by AKV Consultants LLC for Market Street from Lakeside Drive to Magnolia Street, UPIN 23102MF2UQ01, Precinct 2.
end

Background and Discussion:
The project in East Harris County, consists of approximately 5,725 Linear lengths of roadway. AKV Consultants LLC was awarded a contract to provide roadway reconstruction and related improvements along Market Street from Lakeside Drive to Magnolia Street. The goal is to study the existing conditions of Market Street and provide best reconstruction options. Based on that agreement, AKV Consultants LLC submitted the final study report on February 13, 2025.

Expected Impact:



Alternative Options:
The County could elect to approve or choose to reject the study recommendations. However, if not approved, the design plans cannot be completed as recommended in the study.



County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: F: Ensure safety and security for all using the county's transportation network in alignment with the County's Vision Zero plan.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): F...

Click here for full text