Title: Request for approval of a change in contract with Bear Services LP, in connection with final construction of Deputy Tommy Berry Pocket Park - Looped Sidewalk - 2023, with a deduction in the amount of $4,693.40, Job No. 21/0365-1, UPIN 24102MF33A01, Precinct 2, MWBE Contracted Goal: 16%, MWBE Current Participation: 22.57%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 21/0365, UPIN 24102MF33A01
Vendor/Entity Legal Name (if applicable): Bear Services, LP

MWBE Contracted Goal (if applicable): 16%
MWBE Current Participation (if applicable): 22.57%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Bear Services LP, in connection with final construction of Deputy Tommy Berry Pocket Park - Looped Sidewalk - 2023, with a deduction in the amount of $4,693.40, Job No. 21/0365-1, UPIN 24102MF33A01, Precinct 2, MWBE Contracted Goal: 16%, MWBE Current Participation: 22.57%.
end

Background and Discussion:
The project includes the installation of a looped sidewalk and benches within the limits of Rimwood Pocket Park, construction of a bus stop pad, tree plantings, and solar lighting to enhance safety and accessibility. Additional improvements include building a headwall near the bus stop, installing a wooden fence along the Right-of-Way (ROW), and extending the sidewalk to connect the adjacent neighborhood.

PCO -1: Final Adjustment:
This change will allow us to adjust the bid quantities against to work performed by contactor will result in paying the contractor for complete work and deducting the remaining fund in the contract by $4,693.40.

Expected Impact:
Change allows unused funds to be returned to Harris County and allows the Contractor to be compensated for the work performed


Alternative Options:
Continue with the original plan.