Title: Request that the County Judge execute an amendment to an agreement with Johnson Controls, Inc. in the decreased amount of $173,279 to remove two service locations and add one service location for comprehensive maintenance, inspection services and related items for various chillers for Building Operations Services for the period of April 1, 2025 - March 31, 2026 (220339), MWBE Contracted Goal: 7%, MWBE Current Participation: 2.9%.
Attachments: 1. 25-6504 Amendment Job No. 220339 - Johnson Controls, Inc.
Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD

Secondary Department: N/A
Secondary Department Head/Elected Official:

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): 220339
Vendor/Entity Legal Name (if applicable): Johnson Controls, Inc.

MWBE Contracted Goal (if applicable): 7%
MWBE Current Participation (if applicable): 2.9%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request that the County Judge execute an amendment to an agreement with Johnson Controls, Inc. in the decreased amount of $173,279 to remove two service locations and add one service location for comprehensive maintenance, inspection services and related items for various chillers for Building Operations Services for the period of April 1, 2025 - March 31, 2026 (220339), MWBE Contracted Goal: 7%, MWBE Current Participation: 2.9%.
end

Background and Discussion:
Request for approval of the second amendment with Johnson Controls for Comprehensive Maintenance,
Inspection Services and Related Items for Various Chillers for Harris County Building Operations Services.

Expected Impact:
The second amendment removes two (2) service locations (Central Plant and Annex 84) and adds 1010 Lamar.

Alternative Options:
N/A

County Strategic Plan Goal: Choose an item.
County Strategic Plan Objective: Choose an item.
Justice/Safety Initiative (Goal 1): Choose an item.
Infrastructure Initiative (Goal 2): Choose an item.
Economy Initiative (Goal 3): Choose an item.
Health Initiative (Goal 4): Choose an item.
Climate/Resilience Initiative (Goal 5): Choose an item.
Housing Initiative (Goal 6): Choose an item.

Additional notes related to the Str...

Click here for full text