Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job. No. 24/0448, UPIN 19103MF14401
Vendor/Entity Legal Name (if applicable): Environmental Allies Inc.
MWBE Contracted Goal (if applicable): 22.84%
MWBE Current Participation (if applicable): 16.77%
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Environmental Allies Inc., in connection with Cypress Creek Estates Subdivision Drainage Improvements 2018, with an addition in the amount of $53,560.00, Job No. 24/0448-1, UPIN 19103MF14401, Precinct 3, MWBE Contracted Goal: 22.84%, MWBE Current Participation: 16.77%.
end
Background and Discussion:
The project is located in Northwest Harris County in both the White Oak Bayou and Cypress Creek watersheds, west of North Eldridge Parkway and north of Cypress North Houston Road. The existing drainage system consists of roadside ditches. Proposed improvements include an upgraded storm sewer system and re-grade roadside ditches, and reconstruction of Roadway (Subgrade stabilization, black base and surface coarse installation).
The change in contract includes the following:
The line items are adjusted to reconcile underrun quantities and add new line items to the project for completion of the proposed scope of work.
* The decrease of quantities on underrun line items number 16 and 17 for a deduction in the amount of $335,915.00.
* Added new line item - Fly-Ash (8% by Dry Weight) for an addition in the amount of $144,804.06
* Added new line it...