Legislation Details

File #: 25-6169    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/30/2025 In control: Commissioners Court
On agenda: 10/16/2025 Final action: 10/16/2025
Title: Request for approval of a change in contract with Spawglass Construction Corp., in connection with 7400 W Sam Houston Pkwy (Art Storey Park) - New Pavilion - 2022, adding 45 calendar days, with an addition in the amount of $74,293.93. Job No. 24/0202-1, UPIN 23104MF2MF01, Precinct 4, MWBE Contracted Goal: 25.75%, MWBE Current Participation: 25.52%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

Secondary Department: Commissioner, Precinct 4
Secondary Department Head/Elected Official: Commissioner Briones

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0202, UPIN 23104MF2MF01
Vendor/Entity Legal Name (if applicable): Spawglass Construction Corp.

MWBE Contracted Goal (if applicable): 25.75%
MWBE Current Participation (if applicable): 25.52%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Spawglass Construction Corp., in connection with 7400 W Sam Houston Pkwy (Art Storey Park) - New Pavilion - 2022, adding 45 calendar days, with an addition in the amount of $74,293.93. Job No. 24/0202-1, UPIN 23104MF2MF01, Precinct 4, MWBE Contracted Goal: 25.75%, MWBE Current Participation: 25.52%.
end

Background and Discussion:
Project includes the construction of a new 658 sf hexagonal concrete pavilion at Art Storey Park located at 7400 West Sam Houston Parkway in Precinct 4. The concrete pavilion has a custom wooden roof structure with glazed clay tiles that were pre-purchased and imported from Taiwan for installation by the awarded contractor.

The change in contract includes the costs associated with providing the necessary materials, equipment, and labor for additional work involving the installation of the pre-purchased roof structure and tiles. Services include repairing cracks in the wooden roof members, filling of cracks on wood surfaces and sanding smooth prior to painting, for the installation of roof waterproofing, for the application of mortar to roof structure necessary to properly...