Legislation Details

File #: 25-6160    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/30/2025 In control: Commissioners Court
On agenda: 10/16/2025 Final action: 10/16/2025
Title: Request for approval of a change in contract with Environmental Allies, Inc., in connection with Intersection Improvement - Vickery Street at Lauder Road - 2021, with an addition in the amount of $27,347.81, Job No. 24/0084-3, UPIN 22102MF2G801, Precinct 2, MWBE Contracted Goal: 28.35%, MWBE Current Participation: 21.55%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0084, UPIN 22102MF2G801
Vendor/Entity Legal Name (if applicable): Environmental Allies, Inc.

MWBE Contracted Goal (if applicable): 28.35%
MWBE Current Participation (if applicable): 21.55%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Environmental Allies, Inc., in connection with Intersection Improvement - Vickery Street at Lauder Road - 2021, with an addition in the amount of $27,347.81, Job No. 24/0084-3, UPIN 22102MF2G801, Precinct 2, MWBE Contracted Goal: 28.35%, MWBE Current Participation: 21.55%.
end

Background and Discussion:
The project consists of improvements to the intersection of Vickery Street at Lauder Road, including road widening, turning lanes, full-width concrete replacement, sidewalks, bus pads and a traffic signal.

The driveway at 13121 was removed during the design phase. The contractor followed the approved plans, but the homeowner later requested the driveway be restored through the PCT office and paid the required permit fees. To restore access, a drainage system must be installed to maintain proper flow. This change will add an additional cost of $27,347.81 and no additional days.

Expected Impact:
Increase the total cost for the contract.


Alternative Options:
No action will result in substandard construction.

County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrast...

Click here for full text