Legislation Details

File #: 25-6159    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/30/2025 In control: Commissioners Court
On agenda: 10/16/2025 Final action: 10/16/2025
Title: Request for approval of a change in contract with CE Barker, LTD, in connection with HCSFNC - TO3 - Ella Boulevard Providence Place Habitat for Humanity, adding 360 calendar days, with an addition in the amount of $212,710.36, Job No. 23/0434-2, UPIN 20035MF1J501, Precinct 1, MWBE Contracted Goal: 25%, MWBE Current Participation: 15.32%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0434, UPIN 20035MF1J501
Vendor/Entity Legal Name (if applicable): CE Barker, LTD

MWBE Contracted Goal (if applicable): 25%
MWBE Current Participation (if applicable): 15.32%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with CE Barker, LTD, in connection with HCSFNC - TO3 - Ella Boulevard Providence Place Habitat for Humanity, adding 360 calendar days, with an addition in the amount of $212,710.36, Job No. 23/0434-2, UPIN 20035MF1J501, Precinct 1, MWBE Contracted Goal: 25%, MWBE Current Participation: 15.32%.
end

Background and Discussion:
In response to the destruction wrought by Hurricane Harvey that underscored critical shortages in Harris County's inventory of affordable homes, Harris County's Single Family New Construction Program (SFNC) matches individuals and families with opportunities to purchase new affordable homes in growing development throughout the County. This change allows for the construction of infrastructure such as water, sanity, drainage and some landscape features.

Change order includes the following items:

PCO-7: The addition of fill dirt to build up site to proposed elevations. Adding $97,800.00 and 150 days.
PCO-8: Cost to relocate existing 16" waterline for NHCRWA. Adding $101,742.76 and 200 days.
PCO-9: The addition of observation ports for the underdrain system. Adding $13,167.60 and 10 days.


Expected Impact:
Construction of infra...