Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): UPIN 25101MF3VN01
Vendor/Entity Legal Name (if applicable): InfraTech Engineers & Innovators, LLC
MWBE Contracted Goal (if applicable): 19.6%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with InfraTECH Engineers & Innovators, LLC., in the amount of $219,952.00 for Professional Engineering Services to provide drainage assessment, UPIN 25101MF3VN01, Precinct 1, MWBE Contracted Goal: 19.6%.
end
Background and Discussion:
This project will perform a drainage assessment within Precinct 1 unincorporated area. The study will evaluate existing neighborhood drainage conditions, identify areas in need of improvement and prioritize related projects.
Expected Impact:
Improve the drainage conditions and reduce the flood risk for the studied areas after the improvement.
Alternative Options:
No alternative options. If not approved, the study will be delayed or could be cancelled.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): H2: Evaluate the feasibility and potential impacts of substantial, large-scale flood mitigation measures to provi...