Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Interlocal Agreement
Project ID (if applicable): U100-00-00-E009
Vendor/Entity Legal Name (if applicable): Harris County Water Control and Improvement District No. 158
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of an interlocal agreement with the Harris County Water Control and Improvement District No. 158, for a partnership project to study, design, and construct improvements to resolve the Cypress Creek impacts (Addicks Reservoir and Cypress Creek Watersheds, Project ID U100-00-00-E009, Agreement No. 2025-60, Precincts 3 and 4).
end
Background and Discussion:
The Upper Langham Creek Frontier Program provides regional detention benefit for new development within the program service area. As part of the drainage analysis for the last phase of development within the Lang-ham program, it was discovered that improvements to Cypress Creek are required to mitigate impacts from developments within Harris County Water Control and Improvement District No. 158 (HC WCID 158), north of the Langham Program, along Cypress Creek. An agreement is required with HC WCID 158 to specify the terms and conditions of analysis, design, and construction of improvements to Cypress Creek to resolve increases to flood risk downstream of the development and to ensure compliance with Commissioners Court adopted overflow drainage study requirements for areas within the Cypress Creek overflow.