Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Interlocal Agreement
Project ID (if applicable): U100-00-00-E009
Vendor/Entity Legal Name (if applicable): Harris County Water Control and Improvement District No. 159
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of an interlocal agreement with the Harris County Water Control and Improvement District No. 159 for construction of drainage facilities within the Upper Langham Creek Frontier Program (Addicks Reservoir and Cypress Creek Watersheds, Project ID U100-00-00-E009, Agreement No. 2025-61, Precincts 3 and 4).
end
Background and Discussion:
The Upper Langham Creek Frontier Program provides regional detention benefit for new development within the program service area. The service area extends from John Paul Landing basin at the upstream end to Greenhouse basin at the downstream end. Development within the program is planning to expand west/upstream of SH99 within the limits of Harris County Water Control and Improvement District No. 159 (HC WCID 159). An agreement is required with HC WCID 159 to specify the terms and conditions of construction within Flood Control District right-of-way to provide detention mitigation, to specify obligations for associated work within TxDOT SH99 right-of-way, and to compensate Harris County/Flood Control District for the development's use of existing detention mitigation volume within the John Paul Landing detention basin.
Expected Impact...