Legislation Details

File #: 25-5642    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/2/2025 In control: Commissioners Court
On agenda: 9/18/2025 Final action: 9/18/2025
Title: Request for approval of a change in contract with McCrory - CTI Svcs, in connection with Dula Lane and Related Infrastructure Drainage Improvements - 2022, adding 43 calendar days, with an addition in the amount of $10,350.00, Job No. 24/0144-1, UPIN 22208MF2H701, Precinct 3, MWBE Contracted Goal: 26%, MWBE Current Participation: 51.50%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0144, UPIN 22208MF2H701
Vendor/Entity Legal Name (if applicable): McCrory - CTI Svcs

MWBE Contracted Goal (if applicable): 26%
MWBE Current Participation (if applicable): 51.50%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with McCrory - CTI Svcs, in connection with Dula Lane and Related Infrastructure Drainage Improvements - 2022, adding 43 calendar days, with an addition in the amount of $10,350.00, Job No. 24/0144-1, UPIN 22208MF2H701, Precinct 3, MWBE Contracted Goal: 26%, MWBE Current Participation: 51.50%.
end

Background and Discussion:
This project includes the installation of approximately 2,000 Linear feet of underground drainage utilities, and the reconstruction of asphalt pavement, driveway, and regrading of the roadside ditch throughout Dula Lane. Aviles Engineering Corporation will provide construction materials testing services to support the project in construction.

The change in contract includes the following:

The line items are adjusted to reconcile overrun and underrun quantities on the project for completion of the proposed scope of work.

? The increase of quantities for existing line item 12 - "Excavation", for an additional amount of $10,350.00.

? The decrease of quantities for existing line item 20 - "Dense-Graded Hot-Mix Asphalt Surface Course (TY-C SAC-B PG64-22) for a deduction of $65,100.00 and existing line Item 21- Dense-Graded Hot-Mix As...

Click here for full text