Legislation Details

File #: 25-5626    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/2/2025 In control: Commissioners Court
On agenda: 9/18/2025 Final action: 9/18/2025
Title: Request for approval of a change in contract with Innovative Operations, LLC, in connection with final construction of Sanitary Sewer - Crosby Lynchburg Road at Riverside Drive - 2024, adding 13 calendar days, with no change in the amount, Job No. 21/0451-1, UPIN 25103MF3PT01, Precinct 3.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 21/0451, UPIN 25103MF3PT01
Vendor/Entity Legal Name (if applicable): Innovative Operations, LLC

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Innovative Operations, LLC, in connection with final construction of Sanitary Sewer - Crosby Lynchburg Road at Riverside Drive - 2024, adding 13 calendar days, with no change in the amount, Job No. 21/0451-1, UPIN 25103MF3PT01, Precinct 3.
end

Background and Discussion:
This project involves the installation of an 8-inch sanitary sewer line located west of Main Street (Crosby Lynchburg Road), extending from Riverside Street to North Thorn Street. The scope of work includes trenchless (boring) and open-cut construction methods, installation of new sanitary manholes, removal and replacement of existing asphalt driveways, and all associated miscellaneous work required to successfully complete the project in accordance with approved plans and specifications.

This Change in Contract includes:
- PCO #1 / RFI #1 - A total of 13 additional calendar days has been added to the contract duration due to weather-related delays and unforeseen impacts caused by the property owner's delayed removal of a private fence obstructing access to the work area.



Expected Impact:
Adds 13 calendar days to the contract duration with no change in contract value. Acco...