Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 21/0365, UPIN 22102MF2DC01
Vendor/Entity Legal Name (if applicable): Bear Services, LP
MWBE Contracted Goal (if applicable): 16%
MWBE Current Participation (if applicable): 23.27%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Bear Services, LP, in connection with final construction of Sidewalk - Holland Avenue - 2021, adding 60 calendar days, and a deduction in the amount of $134,125.93, Job No. 21/0365-2, UPIN 22102MF2DC01, Precinct 2, MWBE Contracted Goal: 16%, MWBE Current Participation: 23.27%.
end
Background and Discussion:
The construction project along Holland Avenue, extending from Clint Drive to 18th Street, involves the installation of sidewalks and driveways to enhance pedestrian accessibility and safety. This initiative aims to provide a continuous and ADA-compliant pedestrian pathway, improving connectivity for residents and facilitating safer routes for pedestrians.
PCO -18: Adding 10 days
The contractor requires a 10-day contract time extension due to unforeseen site conditions that prevented the installation of the pedestrian pole at the planned location. Existing underground utilities conflicted with the original placement, necessitating an adjustment to the sidewalk layout to accommodate these utilities while ensuring proper installation of the pedestrian pole. The revised location and sidewalk modifications will enhance the pole's accessibility ...