Legislation Details

File #: 25-5607    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/2/2025 In control: Commissioners Court
On agenda: 9/18/2025 Final action: 9/18/2025
Title: Request for approval of a change in contract with Precise Services, Inc., in connection with final construction of Northpointe Boulevard Segment 2, adding 30 calendar days, with an addition in the amount of $44,268.88, Job No. 23/0411-1, UPIN 20104MF1BQ01, Precincts 3 and 4, MWBE Contracted Goal: 31%, MWBE Current Participation: 96.95%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0411, UPIN 20104MF1BQ01
Vendor/Entity Legal Name (if applicable): Precise Services, Inc.

MWBE Contracted Goal (if applicable): 31%
MWBE Current Participation (if applicable): 96.95%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Precise Services, Inc., in connection with final construction of Northpointe Boulevard Segment 2, adding 30 calendar days, with an addition in the amount of $44,268.88, Job No. 23/0411-1, UPIN 20104MF1BQ01, Precincts 3 and 4, MWBE Contracted Goal: 31%, MWBE Current Participation: 96.95%.
end

Background and Discussion:
Project includes construction of half of a concrete boulevard section widening the existing road from a 2-lane road to a 4-lane concrete boulevard road with one new traffic signal and one signal modification.

The final change order is for the adjustment of final quantities of work performed by the contractor in connection with completion of the project and updating quantities to final quantities.

Expected Impact:
Final adjustments are necessary to complete the payment of work performed under the contract and allows us to close the project.

Alternative Options:
Not approving the final quantities will leave this project open and the county will be liable for unpaid work.

County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Ob...