Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 23/0138, UPIN 19101MF14M01
Vendor/Entity Legal Name (if applicable): Blazey Construction Services, LLC
MWBE Contracted Goal (if applicable): 27%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Blazey Construction Services, LLC, in connection with final construction of Evergreen Villas Subdivision Drainage Improvements, with a deduction in the amount of $302,122.13, Job No. 23/0138-05, UPIN 19101MF14M01, Precinct 1, MWBE Contracted Goal: 27%, MWBE Current Participation: 100%.
end
Background and Discussion:
Evergreen Villas is in Northeast Harris County, Texas, Precinct 1. The subdivision is mainly composed of single-family homes. The residents have experienced structural flooding during several recent flood events. Approximately 37 homes were reported to have flooded during Hurricane Harvey. The purpose of this project is to mitigate the risk of house flooding. The proposed solution includes upgrading of storm sewers and adding a detention pond.
The change in contract includes the following:
The line items are adjusted to reconcile overrun and underrun quantities on the project for completion of the proposed scope of work.
? The increase of quantities on overrun line item numbers 003, 005, 009, 015, 022, 023, 034, 044, 049, 050, 055, and 061 for an addition in the amount of $173,203.88.
? The decrease of quantities on un...