Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 22/0369, UPIN 18104MF0R901
Vendor/Entity Legal Name (if applicable): SER Construction Partners, LLC
MWBE Contracted Goal (if applicable): 27%
MWBE Current Participation (if applicable): 48.65%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Rate is not 0% and is listed above.
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with SER Construction Partners, LLC, in connection with final construction of Holderrieth Road Drainage Improvements Project, adding 20 calendar days, with a deduction in the amount of $1,300,272.98, Job No. 22/0369-16, UPIN 18104MF0R901, Precinct 3, MWBE Contracted Goal: 27%, MWBE Current Participation: 48.65%.
end
Background and Discussion:
Project includes the reconstruction of Holderrieth Rd from SH 249 to 850' west of Hufsmith-Kohrville Rd. Reconstruction includes an upgrade of the roadway from a two-lane asphalt road with open ditches to a 4-lane concrete curb and gutter boulevard with a 32' raised median.
The change in contract includes the following:
* Adjust Existing Gas Meters LS $7,714.56
* Concrete Headwall @ Cherry St. LS $5,829.71
* Sawcut and Install Dowel rebars for omitted driveways 37.2 LF $2,380.80
* Adjust Existing Fire Hydrants LS $20,344.37
* Additional Raven liner for sanitary manholes LS $17,734.59
* Tortuga Gas line number 21, 22, 23 relocations LS $160,819.33
* Replace Existing Sanitary Manhole Covers LS $16,931.46
* Additional Sanitary Sewer Vent, ...
Click here for full text