Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 20/0284, UPIN 19101MF12701
Vendor/Entity Legal Name (if applicable): WadeCon, LLC
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with WadeCon, LLC, in connection with final construction of Timber Forest Drive; Bridge Over UPRR; 2018, with an addition in the amount of $85,821.04, Job No. 20/0284-5, UPIN 19101MF12701, Precinct 3, Justification for 0% MWBE Participation Goal: (project was awarded prior to launch of County's M/WBE Program).
... end
Background and Discussion:
Project includes the construction of a new bridge over the UPRR tracks with roadway approaches, medians and
Sidewalks
PCO#10 - FINAL ADJUSTMENT: This change in contract includes the final reconciliation of actual quantities used in construction against the bid quantities. $85,821.04
Expected Impact:
Change allows unused funds to be returned to Harris County and allows the Contractor to be compensated for
the work performed
Alternative Options:
Continue with the original plan.
County Strategic Plan Goal: N/A
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (G...
Click here for full text