Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): UPIN 19103MF14801; Job No. 23/0027
Vendor/Entity Legal Name (if applicable): Raba-Kistner, Inc.
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: 0% - Non-Divisible
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of an amendment to an agreement with Raba Kistner, Inc. in the amount of $61,670.00 for Professional Engineering Services regarding Construction Materials Testing and related Services for Tower Oaks Plaza Subdivision Drainage Improvements - 2018 - UPIN 19103MF14801, Precinct 3, Justification for 0% MWBE Participation Goal: 0% - Non-Divisible.
end
Background and Discussion:
Construction of underground drainage utilities and reconstruction of driveways and roadway in the Tower
Oaks Plaza Subdivision.
Expected Impact:
This agreement will allow the firm to conduct field and laboratory testing on soil, concrete, asphalt and various other construction materials to ensure the material's compliance with Harris County Engineering Department's adopted standards and specifications as required by state law.
Alternative Options:
Construction materials testing is required by state law. Thus, alternatives include issuing a purchase order for similar services to a different vendor or cancelling this construction project.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: H: Improve the co...