Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 4
Secondary Department Head/Elected Official: Lesley Briones
Regular or Supplemental RCA: Regular RCA
Type of Request: Interlocal Agreement
Project ID (if applicable): 25104MF3U701
Vendor/Entity Legal Name (if applicable): Harris County Municipal Utility District No. 71
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an Interlocal Agreement with the Harris County Municipal Utility District No. 71 in connection with the study for extending sidewalks and constructing a pedestrian bridge South of Morton Ranch Subdivision Secs. 1-8 and north of Morton Ranch Schools, UPIN 25104MF3U701, Precinct 4.
end
Background and Discussion:
Harris County is to submit Study for extending sidewalks and constructing an 8' wide prefabricated pedestrian bridge across Harris County Channel U101-05-01 to connect Morton Ranch subdivision to Katy ISD Morton Ranch Elementary, Junior High and High School.
Expected Impact:
This project will provide pedestrian connectivity. It will also significantly impact pedestrian safety, physical activity and social interaction.
Alternative Options:
Harris County may elect not to move forward, and Harris County can explore additional options, however this will cause project delays.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goa...
Click here for full text