Title: Request for approval of the Final Investment Memo for the Telephone System Repair/Replace project for an incremental authorization of $560,000 for a total authorization of $760,000 for FY 2026.
Primary Department: Universal Services
Primary Department Head/Elected Official: Sindhu Menon, Executive Director and CIO

Managing Department: Universal Services
Managing Department Head/Elected Official: Sindhu Menon, Executive Director and CIO

Regular or Supplemental RCA: Regular RCA
Type of Request: Investment Memo
Investment Memo Type: Final Investment Memo

Project Name: Telephone System Repair/Replace
Project ID (if applicable): NI026
Vendor Legal Name (if applicable): N/A

MWBE Contracted Goal (if applicable): N/A
MWBE Current Achievement (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Incremental Authorization Requested: $560,000
Total Estimated Project Cost: $1,520,000 (FY26 & FY27)


Request Summary:
title
Request for approval of the Final Investment Memo for the Telephone System Repair/Replace project for an incremental authorization of $560,000 for a total authorization of $760,000 for FY 2026.
end
Project Description:
This project replaces end-of-life voice equipment including phones, media gateways, session border controllers, and related solutions within the data centers and across 200+ locations.
Voice equipment is replaced on an approximately 15-year cycle, requiring the replacement of handsets and related peripheral equipment.
Data center infrastructure would continuously need to be expanded in capacity due to the constant increase in the county's needs.

Anticipated Project Expenditures and Timeline:
Project Scope Breakdown
Estimated Cost
Estimated Completion
1,700 Phone replacement
$459,000
08/31/2026
Gateway and Session Border Controller upgrades
$150,000
07/31/2026
FISK-Swapping out phones
$81,600
09/30/2026
10% Contingency
$69,400
09/30/2026
FY26 Total Authorization
$760,000

Unencumbered existing project balance to carry into FY26
($200,000)

Total
...

Click here for full text