Title: Request for approval to execute a Service Outlet Location Statement for installation of an electric meter with CenterPoint Energy, LLC and authorize the County Auditor to pay monthly bills at 104 1/2 Gulf Bank Road (Intersection of West Gulf Bank at Airline Drive) for electrical power serving a traffic signal, UPIN 19101MF0XV01, Precinct 2.
Attachments: 1. 25-5156-SOLS -UPIN 19101MF0XV01-W Gulf Bank Rd from I45 to Airline Dr-P2
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Utility Agreement

Project ID (if applicable): Job No. 22/0461, UPIN 19101MF0XV01
Vendor/Entity Legal Name (if applicable): CenterPoint Energy, LLC

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute a Service Outlet Location Statement for installation of an electric meter with CenterPoint Energy, LLC and authorize the County Auditor to pay monthly bills at 104 1/2 Gulf Bank Road (Intersection of West Gulf Bank at Airline Drive) for electrical power serving a traffic signal, UPIN 19101MF0XV01, Precinct 2.
end

Background and Discussion:
This project includes the construction of four 11-foot-wide concrete pavement with a 24-foot median, and 8-foot-wide sidewalk along both sides West Gulf Bank Road from Interstate 45 Freeway to Airline Drive. It also includes the drainage improvements.

During construction, a field conflict was identified that impacted the original planned location of the traffic signal meter. This conflict required relocating the meter to a more suitable location to ensure safety, accessibility, and compliance with utility requirements.

Expected Impact:
Approval of the service outlet location statement will allow CenterPoint Energy to provide electrical service to the traffic
signal, which is needed to enhance the public safety and operation of the intersection of Intersection of West Gulf Bank at Airline Drive



Alternative Options: