Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 23/0027, UPIN 19103MF14801
Vendor/Entity Legal Name (if applicable): Blazey Construction Services, LLC
MWBE Contracted Goal (if applicable): 31%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Blazey Construction Services, LLC, in connection with Tower Oaks Plaza Subdivision Drainage Improvements - 2018, with an addition in the amount of $244,848.70, Job No. 23/0027-4, UPIN 19103MF14801, Precinct 3, MWBE Contracted Goal: 31%, MWBE Current Participation: 100%.
end
Background and Discussion:
The project is located in northwest Harris County, north of Cypress North Houston Road and east of North Eldridge Parkway. The existing drainage system consists of roadside ditches which outfall to the west of the subdivision via 24 to 36-inch pipes at three points along HCFCD Channel K161-00-00 and to Cypress Creek from a fourth outfall at the northeast corner of the subdivision. The scope and proposed improvements include bringing the subdivision roadways into compliance with Harris County Standards, constructing storm sewer underlying roadside ditches, regarding roadside ditches, upsizing and replacing driveway culverts, replacing driveways, and the construction of a storm water detention basin.
The change in contract includes the following:
New Line Items: Adding new line items on the project for completion of the proposed scope of ...
Click here for full text