Legislation Details

File #: 25-5138    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 8/13/2025 In control: Commissioners Court
On agenda: 8/26/2025 Final action: 8/26/2025
Title: Request for approval of a change in contract with AAA Asphalt Paving, Inc., in connection with Asphalt Package 2024 - 4, adding 25 calendar days, with an addition in the amount of $27,540.00, Job No. 24/0325-1, UPIN 24208MF36K01, Precinct 3, MWBE Contracted Goal: 34%, MWBE Current Participation: 25.37%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0325, UPIN 24208MF36K01
Vendor/Entity Legal Name (if applicable): AAA Asphalt Paving, Inc.

MWBE Contracted Goal (if applicable): 34%
MWBE Current Participation (if applicable): 25.37%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with AAA Asphalt Paving, Inc., in connection with Asphalt Package 2024 - 4, adding 25 calendar days, with an addition in the amount of $27,540.00, Job No. 24/0325-1, UPIN 24208MF36K01, Precinct 3, MWBE Contracted Goal: 34%, MWBE Current Participation: 25.37%.
end

Background and Discussion:
This project consists of asphalt rehabilitation work at several key locations. The scope includes Malcomson Road from Grant Road to Louetta Road, Fenske Road from Cypress Church Road to Cypress Rose Hill Road, and Cypress Church Road from Louetta Road to Mueschke Road. The Precinct requested the replacement of the existing single 48" pipe at the intersection of Cypress Church and Fenske Rd with a double run of 36" RCP

PCO-1- Cypress Church/Fenske Rd Cross-Pipe Replacement.
Items:
Item #43: Install 36" RCP Quantity: 82 LF @$245/LF = $22,540.00
New Item - Ditch Regrading Quantity: 125 LF @ 40/LF = $5,000.00

Cost: $27,540.00 / Time: 25 additional days added to the contract



Expected Impact:
These changes allow for quantity adjustments and the inclusion of new bid items necessary to complete the project in line with its original intent and in compl...