Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 24/0105, UPIN 22289MF29Q01
Vendor/Entity Legal Name (if applicable): Reliance Construction Services, LP
MWBE Contracted Goal (if applicable): 25.62%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Reliance Construction Services, LP, in connection with Water Distribution and Sanitary Sewer System Construction - West Bertrand - 2022, adding 90 calendar days, with an addition in the amount of $91,816.80, Job No 24/0105-2, UPIN 22289MF29Q01, Precinct 2, MWBE Contracted Goal: 25.62%, MWBE Current Participation: 100%.
... end
Background and Discussion:
This project includes the construction of a new water distribution and sanitary sewer system to serve West Bertrand Street and West Marianne Street and service connections, and the decommissioning of existing wells and abandonment of eligible residents. This change in contract includes:
PCO#3: The number of sewer service connections authorized for installation on this project has increased by approximately 67% over the originally targeted contract quantity. This substantial change is due to a higher level of resident participation than initially anticipated.
As a result, additional coordination with the City of Houston (COH), residents, and other project stakeholders is required, along with the extra time needed to complete each connection. To properly accommodate this increased sco...
Click here for full text