Legislation Details

File #: 25-5132    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 8/13/2025 In control: Commissioners Court
On agenda: 8/26/2025 Final action: 8/26/2025
Title: Request for approval of a change in contract with Reliance Construction Services, LP, in connection with Water Distribution System - Parkwood Estates Phase 4 Olana Drive - 2022, adding 90 calendar days, with no change in the amount, Job No 24/0101-1, UPIN 22289MF29P01, Precinct 2, MWBE Contracted Goal: 23.13%, MWBE Current Participation: 100%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0101, UPIN 22289MF29P01
Vendor/Entity Legal Name (if applicable): Reliance Construction Services, LP

MWBE Contracted Goal (if applicable): 23.13%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Reliance Construction Services, LP, in connection with Water Distribution System - Parkwood Estates Phase 4 Olana Drive - 2022, adding 90 calendar days, with no change in the amount, Job No 24/0101-1, UPIN 22289MF29P01, Precinct 2, MWBE Contracted Goal: 23.13%, MWBE Current Participation: 100%.
...end

Background and Discussion:
The project consists of installing a water distribution system to serve Olana Drive in Precinct 2 of Harris County. The water distribution system includes the installation of waterline along Olana Drive, water service connections to existing residences and the decommissioning of existing wells. Over all 44 Connection Expected is completed
This change in contract includes:
PCO#1: This request for a 90-day time extension is due to delays primarily related to the service connection process, beginning with issues on the property owners' side. Several property owners submitted incomplete meter applications, failed to apply in a timely manner, or provided incorrect or late deposit payments. These errors are difficult to correct are beyond the contractor's control.
In addition, the City of Houston's (COH) interna...

Click here for full text