Legislation Details

File #: 25-5129    Version: 1 Name:
Type: Transmittal Status: Accepted
File created: 8/13/2025 In control: Commissioners Court
On agenda: 8/26/2025 Final action: 8/26/2025
Title: Transmittal by the Flood Control District of a certificate of substantial completion with Russell Marine, LLC for the A200 Gated Structure General Maintenance Project (Clear Creek Watershed, Project ID A200-00-00-X028, Job No. 23/0487, Precinct 2).
Attachments: 1. A200-00-00-X028 Sub Completion Cert SIGNED.pdf
Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Transmittal

Project ID (if applicable): A200-00-00-X028
Vendor/Entity Legal Name (if applicable): Russell Marine, LLC.

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Transmittal by the Flood Control District of a certificate of substantial completion with Russell Marine, LLC for the A200 Gated Structure General Maintenance Project (Clear Creek Watershed, Project ID A200-00-00-X028, Job No. 23/0487, Precinct 2).
end

Background and Discussion:
The purpose of this transmittal is to notify the Commissioners Court of the substantial completion of construction activities for Project A200-00-00-X028 General Maintenance at the Clear Creek Gated Structure.
The gated structure was installed to preserve Clear Lake's natural hydraulic and environmental conditions.

The project scope for this effort included replacing six massive carbon steel flood control gates - each one measuring approximately 20 ft by 21 ft and weighed nearly 10 tons. Construction began on April 21, 2025, and reached substantial completion on June 4, 2025.

Expected Impact:
Substantial Completion signifies that a flood control project is largely finished, allowing the Flood Control District to begin using the majority of the infrastructure to realize intended flood risk reduction benefits while the Contractor completes any applicable minor outstanding details.


Alternative Options:
There is no viable alternative to accepting substantia...

Click here for full text