File #: 25-5003    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 8/1/2025 In control: Commissioners Court
On agenda: 8/14/2025 Final action: 8/14/2025
Title: Request for approval to execute an amendment to an agreement with Omega Engineers, Inc. in the amount of $39,312.37 for Professional Engineering Services to provide improvements to Mueschke Road Segment 9 - from 500' north of Draper Road to approximately 1000' north of FM 2920 - UPIN 171033020712, Precinct 4, Justification for 0% MWBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.

Harris County Commissioners Court
Request for Court Action
Primary Department: County Engineer
Primary Department Head/Elected Official: Dr. Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official:

Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment

Project ID (if applicable): UPIN 171033020712
Vendor/Entity Legal Name (if applicable): Omega Engineers, Inc.

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute an amendment to an agreement with Omega Engineers, Inc. in the amount of $39,312.37 for Professional Engineering Services to provide improvements to Mueschke Road Segment 9 - from 500' north of Draper Road to approximately 1000' north of FM 2920 - UPIN 171033020712, Precinct 4, Justification for 0% MWBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
end


Background and Discussion:
Harris County desires to amend the professional service agreement to remove the inclusion of sidewalks on both sides of Mueschke Road from 2700' south of Draper Road to approximately 1000' north of FM 2920.
This amendment includes the revision of the storm sewer drainage design to provide an adequate transition due to the extended limits.


Expected Impact:
This action item will improve the traffic in the area, alongside the removal of sidewalks and revision to the storm sewer drainage design.

Alternative Options:
If no action is taken, the project will proceed based on existing drawings and move to construction without the necessary revisions to sidewalks, driveways, and the drainage s...

Click here for full text