Legislation Details

File #: 25-4921    Version: 1 Name:
Type: Investment Memo Status: Passed
File created: 7/28/2025 In control: Commissioners Court
On agenda: 8/7/2025 Final action: 8/7/2025
Title: Request for approval of a Final Investment Memo for the Precinct 4 Tomball Service Center Car Wash System project, for an amount of $305,000, and commercial paper funding in the amount of $305,000.
Primary Department: Commissioner, Precinct 4
Primary Department Head/Elected Official: Commissioner, Lesley Briones

Managing Department: Commissioner, Precinct 4
Managing Department Head/Elected Official: Commissioner, Lesley Briones

Regular or Supplemental RCA: Regular RCA
Type of Request: Investment Memo
Investment Memo Type: Final Investment Memo

Project Name: Precinct 4 Tomball Service Center Car Wash System
Project ID (if applicable): CARWASH_TSC
Vendor Legal Name (if applicable): N/A

MWBE Contracted Goal (if applicable): N/A
MWBE Current Achievement (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Incremental Authorization Requested: $305,000
Total Estimated Project Cost: $305,000

Request Summary:
title
Request for approval of a Final Investment Memo for the Precinct 4 Tomball Service Center Car Wash System project, for an amount of $305,000, and commercial paper funding in the amount of $305,000.
end

Project Description:
Precinct 4 seeks to purchase and install a heavy-duty automated car wash system at the Tomball Service Center located at 14444 Holderrieth Road, Tomball, TX 77377. Precinct 4 supports a fleet of buses and support vehicles used for park operations, road and bridge maintenance, and community programming. The buses routinely transport youth and senior residents to community events across Harris County.
Currently, no vehicle wash infrastructure exists at Precinct 4, and a new car wash system will provide a reliable, efficient, and environmentally conscious vehicle washing capability for the precinct's fleet, improving cleanliness, vehicle longevity, and public presentation.
Anticipated Project Expenditures and Timeline: Project Breakdown
Project Breakdown
Estimated Cost
Estimated Completion
3-Brush Wash System
$219,204
March 2026
Support Equipme...