Legislation Details

File #: 25-4382    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/1/2025 In control: Commissioners Court
On agenda: 8/7/2025 Final action: 8/7/2025
Title: Request for approval of a change in contract with Texas Materials Group, Inc., in connection with final construction of Asphalt Package 2023-2, adding 132 calendar days, with a deduction in the amount of $410,133.01, Job No. 23/0293-1, UPIN 23103MF2WQ01, Precinct 3, MWBE Contracted Goal: 33%, MWBE Current Participation: 14.17%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0293, UPIN 23103MF2WQ01
Vendor/Entity Legal Name (if applicable): Texas Materials Group, Inc.

MWBE Contracted Goal (if applicable): 33%
MWBE Current Participation (if applicable): 14.17%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Texas Materials Group, Inc., in connection with final construction of Asphalt Package 2023-2, adding 132 calendar days, with a deduction in the amount of $410,133.01, Job No. 23/0293-1, UPIN 23103MF2WQ01, Precinct 3, MWBE Contracted Goal: 33%, MWBE Current Participation: 14.17%.
end

Background and Discussion:
Project includes roadway rehabilitation, mill, and overlay with base repair for Dallas Road, Louis Road, Old Atascocita Road, Parish Road, Marshall Road, and Smith Street.

The change in contract includes the following:
* Addition of 132 days for encountering extra base repair, installation of bridge headwalls and delay caused by CenterPoint operation on Old Atascocita Road, installation of Guardrail and CMP extension on Dallas Hanna Nash Road, and subgrade installation on Smith Road (132 days).
* The final adjustment (reconciliation of actual quantities used in construction against the bid quantities). (-$410,133.01).

Expected Impact:
Change allows unused funds to be returned to Harris County and allows the Contractor to be compensated.

Alternative Options:
Maintain the original scope of the project.

County Strategic Plan G...

Click here for full text