Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Transmittal
Project ID (if applicable): B512-02-00-E001
Vendor/Entity Legal Name (if applicable): Mar-Con Services, LLC
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Transmittal by the Flood Control District of a certificate of substantial completion with Mar-Con Services, LLC, for Brookglen Stormwater Detention Basin Phase 1 North Compartment (Armand Bayou Watershed, Bond ID C-06, Job No. 23/0428, Project ID B512-02-00-E001, Precinct 2).
end
Background and Discussion:
Brookglen Stormwater Detention Basin includes the construction of a dry bottom basin with maintenance path and a floatable screen system on a former neighborhood cul-de-sac. The purpose of this transmittal is to submit the Certificate of Substantial Completion, confirming that the Contractor has fulfilled the scope of work and resolved all punch list items to the satisfaction of the Flood Control District.
Expected Impact:
Substantial Completion signifies that a flood control project is largely finished, allowing the Flood Control District to begin using most of the infrastructure to realize intended flood risk reduction benefits while the Contractor completes any applicable minor outstanding details. The improvements made through this project will reduce flood risk across multiple tributaries in the Cypress Creek Watershed.
Alternative Options:
There is no viable alternative to accepting substantial completion when a Contrac...